Bitdeer Breaks Ground on $155M Alberta Computing Hub With On-Site 101 MW Gas Power

BTC-6.52%
According to The Energy Mag, Bitdeer broke ground on Tuesday near Fox Creek on a 101 megawatt natural gas power plant combined with a 100 megawatt data center facility. The $155 million investment, or about C$214 million, is expected to be energized in the second quarter of 2027. The facility will initially support bitcoin mining while retaining flexibility to host future high-performance computing and AI applications, operating under Alberta's bring-your-own-generation framework with on-site power generation and a 99 megawatt grid interconnection.
Disclaimer: The information on this page may come from third-party sources and is for reference only. It does not represent the views or opinions of Gate and does not constitute any financial, investment, or legal advice. Virtual asset trading involves high risk. Please do not rely solely on the information on this page when making decisions. For details, see the Disclaimer.